2026 Roadway Improvements
The City of Lakeville completes annual road improvement projects to maintain safe, accessible and reliable streets across the community. The 2026 projects include road repairs, rehabilitation and reconstruction on local and collector streets, trails and parking areas, along with curb, sidewalk, ADA ramp, water system and stormwater improvements. Use the tabs below to learn more about each project planned for the year.
The 2026 Miscellaneous Road Repairs and Overlays Project (City project 26-01) is comprised of approximately 2.5 miles of local and collector streets, .9 miles of local trails and rehabilitation of the Bunker Hill Park parking lot within the City of Lakeville. This project generally includes pavement milling and overlay, partial curb replacement, spot sidewalk replacement, ADA pedestrian ramp updates, watermain corrosion protection and minor storm sewer repairs.
Helpful Information
- Phasing map (PDF)
- FAQs
Project Timeline
- August - October 2025: Preliminary engineering
- Winter 2025/2026: Final design
- February 26, 2026: Receive and publicly open bids
- March 5 2026: Neighborhood meeting
- April 6, 2026: City Council to review bids and consider award of contract
- April-June 2027:Construction
- Note: Schedule subject to change, more details will be posted on this webpage when available
Private Features Within City Right-of-Way
- Lawn irrigation or sprinkler systems
- Pet containment systems
- Landscaping and plantings
If you wish to protect private features from damage during construction, please temporarily remove them from the City right-of-way. City staff will mark areas of anticipated excavation with white paint and flagging. See the video below for more details.
Neighborhood Meeting
March 5, 2026
4:30-6:30 p.m.
Lakeville Water Treatment Facility
18400 Ipava Avenue
Sign up for Project Updates
Sign up for email updates to stay in the know on projects!
Project Newsletters
Newsletters will be available after preconstruction meetings are concluded.
Contact Us
If you have any questions regarding the project, contact Jake Johnson, Senior Construction Representative, at 952-985-2794 or by email.
The 2026 Street Reconstruction Project is comprised of approximately 0.13 miles of local streets within the City. The project scope includes street reconstruction in the form of reclamation, subgrade excavations as required, new pavement installation, including partial replacement and installation of concrete curb and cutter, installation of corrosion protection on select watermain facilities and stormwater management improvements.
Helpful Information
- Project location map (PDF)
- Project flyer (PDF)
- 2026 Frequently Asked Questions (FAQs)
- Feasibility Report (PDF)
- Street reconstruction assessment policy (PDF)
- Special assessment deferment (PDF)
Project Schedule (Tentative) and Proposed Project Improvements
(Click on image below to see them larger.)
Project Timeline
- November 3, 2025: Present feasibility report and set public hearing
- November 5, 2025: Stakeholder meeting at Central Maintenance Facility 10-11 a.m.
- December 1, 2025: Public Hearing
- January 20, 2026: City Council Approves Plans and Specifications
- February 26, 2026: Open bids
- March 3, 2026: Second Stakeholder Meeting Central Maintenance Facility 11 - noon
- April 6, 2026: Assessment hearing and Council considers award of the construction contract
- April 2026: Begin construction
- May 2026: Substantial completion
- June 2026: Final Completion
Dates are subject to change.
Stakeholder Meetings/Public Hearings
November 5, 2025
Neighborhood Meeting
10-11 a.m.
Central Maintenance Facility
7570 179th Street W
December 1, 2025
Public Hearing at City Council meeting
6 p.m.
Lakeville City Hall
20195 Holyoke Avenue
Late February, 2026
Neighborhood Meeting
Lakeville Water Treatment Facility
18400 Water Treatment Facility
March 2, 2026
Public Hearing at City Council meeting
6 p.m.
Lakeville City Hall
20195 Holyoke Avenue
Sign up for Project Updates
Sign up to get email updates and stay in the know on projects!
Project Newsletters
Not available yet.
Contact Us
If you have any questions regarding the project, contact Stephen Ferraro at 952-985-2793 or by email.
The 2026 Street Rehabilitation Project is comprised of approximately 5.25 miles of local and collector streets within the City. The project scope includes milling the existing pavement , installation of new pavement overlay, spot/gutter replacement, spot sidewalk replacement, water system enhancements, pedestrian curb ramp reconstruction to meet current ADA guidelines and storm water management best practices requirements.
Helpful Information
Construction Schedule
Dates are subject to change.
Project Timeline
February 25, 2026: Open bids
March 10, 2026: Neighborhood meeting
March 16, 2026: Award contact
April/May 2026: Begin Construction
October 2026: Substantial coompletion
November 2026: Final construction
- Note: Schedule subject to change, more details will be posted on this webpage when available
Private Features Within City Right-of-Way
- Lawn irrigation or sprinkler systems
- Pet containment systems
- Landscaping and plantings
If you wish to protect private features from damage during construction, please temporarily remove them from the City right-of-way. City staff will mark areas of anticipated excavation with white paint and flagging. See the video below for more details.
Neighborhood Meetings
Tuesday, March 10 2026
4:30-6:30 p.m.
Lakeville Water Treatment Facility
18400 Ipava Avenue
Project Updates
Sign up for project update emails to stay in the know on the project!
Project Newsletters
Newsletters will be available after preconstruction meetings are concluded.
Contact Us
If you have any questions regarding the project, contact Steve Ferraro, Public Works Coordinator, at 952-985-2793 or by email.
-
Paul Oehme
Public Works DirectorPhone: 952-985-2700
-